2004
The City Council commissions the municipal authorities to announce a town planning competition for the Technical Town Hall.


2005
A jury chooses the design by the firm of architects KSP Engel & Zimmermann. A public debate on the planning begins. The reconstruction of historical old town houses is demanded.


2006
Historical documents are examined and a planning workshop set up with the collaboration of some 60 residents of the city.


2007
The city repurchases the Technical Town Hall. The City Council decides on plans based on the planning workshop.


2009
In July, a Europe-wide competition for the Stadthaus am Markt is launched and DomRömer GmbH is formed in order to develop the DomRömer area. A planning board is set up and design specifications submitted through the municipal authorities.

In December Michael Guntersdorf is appointed managing director of DomRömer GmbH. A jury decides on four winning designs for the construction of the Stadthaus am Markt over the Archaeological Garden.


2010
In April the groundbreaking ceremony is held and demolition of the Technical Town Hall begins. In November DomRömer GmbH launches the architectural competition for the redevelopment of the DomRömer area. More than 170 firms of architects from all over Europe apply to participate in the competition.


2011
At the beginning of February, the DomRömer Special Commission appoints the consortium of Meurer Architekten Stadtplaner Ingenieure together with cba architectes from Frankfurt am Main / Luxembourg to take over the further planning of the Stadthaus am Markt. The City Council approves the decision on 24 February with a huge majority. The results of the DomRömer development competition are presented to the public on 23 March. Beforehand a jury selected the 54 best designs from the models submitted. DomRömer GmbH invites the winners to submit tenders, holds talks with the tenderers and draws up proposals for awarding the offer which are put to the advisory council. At the same time the tender procedure for the planning of the reconstructions begins.

The Römer underground car park closes in May for further building work and the remaining ground floor of the former Technical Town Hall is pulled down. In December sales negotiations are completed for the optional reconstructed buildings. Based on these talks, DomRömer GmbH draws up a decision paper. The final decision is made: 15 houses will be reconstructed by 2017.


2012
In January the foundation stone for the new DomRömer Quarter is ceremonially laid. The Advisory Council accepts the contract award recommendations put forward by DomRömer GmbH following the DomRömer Development competition; the planning committee also agrees. The winners of the competition are also awarded the contract. On 24 February the results are presented to the Dom-Römer Special Commission and for the first time to the public. The old town now has a face.

In summer the preparatory work for the Stadthaus and the southernmost row of houses Markt and Krönungsweg begins. The Archaeological Garden is inspected and prepared for the foundation work. In August the so-called Schirn-Tisch, a large rectangular concrete veranda, is demolished.

In August the Archaeological Garden is packed in geotextile and carefully filled in with a gravelly substance so that it has the best possible protection during the foundation works at the southern end. In the northern section of the DomRömer Quarter 90 % of the basements for the new old town houses have been completed. You can watch the activities at the building site on our webcams, by the way.


2013
At the beginning of the year the foundation piles for the Stadthaus and the houses on the southern side of the Markt are laid. Deep holes were bored in the ground. At a depth of around 30 metres, approximately 30 concrete supports were put in the ground to bear the weight of the Stadthaus and the terraced houses on Krönungsweg. In April the Archaeological Garden is freed from its protective cover of gravel and geotextile.

After extensive foundation work in the Archaeological Garden, building begins on the shell of the Stadthaus am Markt in May.

DomRömer car park reopens in July with a new shine. The extensive restoration work has been completed and 480 parking spaces are now available. User-friendly family parking spaces and new electric filling stations for e-cars are among some of the new features. Mayor Olaf Cunitz: "One of the most modern and user-friendly car parks in our city".

August 2013: The DomRömer website takes on a new look. The website is now interactive and contains a wealth of pictures and information about the new quarter in the heart of the city enabling a very good overview of the project quickly and easily.

Visitors to the nearby citizens' advice office on Römerberg are also constantly asking for more information about the DomRömer project. DomRömer GmbH, supported by the Press and Information Office, has consequently set up its own Info Point in the citizens' advice office in the Frankfurt Forum am Römerberg.

In September a further milestone will be reached: The architectural designs for the 20 new buildings in the quarter have undergone detailed planning over the past months and the approval plans have been completed. This means the planning application for the entire DomRömer Quarter can now be submitted.


2014
February 2014: The new Dom/Römer underground exit is opened. The exit had to be moved in order to build the new Goldene Waage house. The first section - the emergency stairway - is commissioned. Over the next few months the escalator will be moved to the new exit and the old exit dismantled. Building can then start on the Goldene Waage – the famous Renaissance building in the old town - and other houses along the Krönungsweg.

Marketing of the apartments in the 20 new buildings in Frankfurt's old town starts in February.

March 2014: Information event for potential buyers and sales negotiations. There is a great deal of interest.

June 2014 In order to offer residents, tourists and visitors as pleasant an environment as possible during the construction work, DomRömer GmbH commissions the artists Ingrid Strohkark and Nicole Wächtler to design a section of the building fence near the Dom/Römer underground station. In cooperation with the restaurant opposite, Cucina Delle Grazie, a colourful work of art is created that visitors can stop and admire.

The Stadthaus am Markt, a central part of Frankfurt's future old town, is entering the crucial construction phase. At the end of June 2014 the structural work on the last and biggest section of the building is completed. Then the great moment comes. The event hall which will later accommodate 150 people and literally "hangs" above the remains in the Archaeological Garden" is "mounted" in the existing shell as a steel construction.

July 2014 this year's Iconic Award in the category "Communication" goes to DomRömer GmbH. They impressed the expert jury for spatial design with their transparent project communication on the reconstruction of Frankfurt's old town. The marketing strategy developed by DomRömer GmbH in collaboration with the agencies Standard Rad and FuP Marketing und Kommunikation "The city is alive. Welcome to Frankfurt's new centre" triumphed against the many other creative entries.

An important milestone along the road to Frankfurt's new old town is reached: The planning authorities of the City of Frankfurt give DomRömer GmbH construction approval for the whole project. After building has begun on the Stadthaus, the overground works on the 35 old houses between the cathedral and Römer can also begin.

Structural work on the Stadthaus am Markt, the event and meeting venue at the southern end of the area, is nearing completion. The topping-out ceremony for the Stadthaus will be held in autumn this year.

But it's not just on the building site between the Cathedral and the Römer that people are busy at work. Preparations for the construction of the 35 old houses are also going on in various craft workshops. At Hermann Graser's natural stone works in Bamberg, for example. With his expert hands the stonemason is creating decorative stones, figures, fountains and columns which will all have a place in the façades and courtyards of the new Frankfurt old town. During a visit to the Bamberg works, journalists had the opportunity to watch him at work. The stone masonry for the Goldene Waage, the Goldene Lämmchen and the house Klein Nürnberg is completed first.

September 2014: The new Frankfurt old town is given colour. For those interested there was an opporutnity to look at wall models for the colour master plans of the DomRömer Quarter together with experts in colour and architectural design and project development at Hildesheim University.

October 2014: The shell of the Stadthaus am Markt is finished. The topping-out ceremony takes place in beautiful sunshine and is another important milestone in Frankfurt's old town project. Lots of guests celebrate at the building site together with the City of Frankfurt. Mayor Olaf Cunitz talks of a "great contribution to Frankfurt's culture of remembrance“.

November 2014: Start of overground work on the old houses.

Outlook
All the buildings and the development of the exterior areas will be completed in 2017.